தினமலர்
சினிமா
டிவி
Podcast
iPaper
கோயில்கள்
புத்தகங்கள்
Subscription
திருக்குறள்
கடல் தாமரை
Dinamalar Logo

 

/செய்திகள்/Kalvimalar/News/Rosatom completes control system installation at Bangladesh's first nuclear plant

Rosatom completes control system installation at Bangladesh's first nuclear plant

Rosatom completes control system installation at Bangladesh's first nuclear plant


UPDATED : அக் 16, 2026 12:12 AM

ADDED : அக் 16, 2026 12:13 AM

Google News

UPDATED : அக் 16, 2026 12:12 AM ADDED : அக் 16, 2026 12:13 AM


Google News
நிறம் மற்றும் எழுத்துரு அளவு மாற்ற

Moscow: Russia's state-owned nuclear energy corporation Rosatom has completed the installation of automated process control systems at both units of the Rooppur Nuclear Power Plant in Bangladesh, marking a key step in the construction of the country's first nuclear power plant.

The plant, being built by Rosatom's engineering division, will have two Generation III+ VVER-1200 reactors with a combined capacity of 2,400 MW.

The automated control systems, supplied by Rosatom Automated Control Systems (RASU), include around 20,000 pieces of equipment across 43 systems. They will monitor more than 7,000 process parameters, including reactor stability, and support the safe and efficient operation of the plant.

A key component is the Operator Information Support System (OISS), developed by RASU using a digital twin of the power unit. The system has been integrated into Unit 1 and is participating in start-up operations. It will also be installed at Unit 2.

The OISS processes data from 360 technological systems, identifies deviations and provides operators with recommendations based on more than 80 instructions, including emergency response procedures. The system is designed to help operators assess situations quickly and make informed decisions.

"The Rooppur NPP is not only the largest project of cooperation between the Russian Federation and the Republic of Bangladesh, but also our flagship in the use of modern automation and control technologies," Rosatom Director General Alexey Likhachev said.

He noted that Rooppur was Rosatom's first overseas nuclear power plant to implement the Operator Information Support System, adding that the technology could improve response times and reduce operating costs.

Located about 160 km from Dhaka, the Rooppur plant is being constructed under a general contract signed on December 25, 2015. The VVER-1200 reactor design is a Generation III+ technology that Rosatom says meets international safety requirements.

Rosatom said the project reflects its growing international cooperation in nuclear energy and advanced automation technologies.